A planned eight-minute test firing of the four engines of NASA’s Space Launch System (SLS) – a megarocket more powerful than the Saturn V that propelled the Apollo astronauts to the moon – did not go as planned on Saturday, January 16, 2021. The test was conducted at NASA’s Stennis Space Center in Mississippi. The rocket is the one meant to launch the next man and first woman on a return to the moon by 2024 in NASA’s Artemis program. The four engines on the booster stage were supposed to fire for the eight minutes they’d need to fire during an actual launch. Instead, the engines fired for only about a minute.
NASA said in a statement:
The team successfully completed the countdown and ignited the engines, but the engines shut down a little more than one minute into the hot fire. Teams are assessing the data to determine what caused the early shutdown, and will determine a path forward.
NASA Administrator Jim Bridenstine, who attended the test, said:
Saturday’s test was an important step forward to ensure that the core stage of the SLS rocket is ready for the Artemis 1 mission [an uncrewed test mission whose launch had been planned for later this year], and to carry crew on future missions. Although the engines did not fire for the full duration, the team successfully worked through the countdown, ignited the engines, and gained valuable data to inform our path forward.
Read more from NASA about the specifics of the January 16 test of NASA’s SLS megarocket
"I want people to be encouraged because the future is very bright, and certainly we're going to learn a lot from this test." – Administrator @JimBridenstine reflects on today's hot fire of the @NASA_SLS rocket core stage. pic.twitter.com/vYfpxr56nG
— NASA (@NASA) January 17, 2021
.@NASA_SLS program manager John Honeycutt provides a summary of today's rocket core stage test at @NASAStennis: pic.twitter.com/RwpFwoiEli
— NASA (@NASA) January 17, 2021
"The test article that is behind us is also the flight hardware that will launch Orion to the Moon. This is unique. […] This article made the right decision to shut itself down." – Administrator @JimBridenstine on today's @NASA_SLS core stage test. pic.twitter.com/hv7mRx7gAn
— NASA (@NASA) January 17, 2021
The January 16 test – called a hot-fire test – was meant to be the culmination in a series of tests for the SLS megarocket. Originally scheduled to take place in early to mid-November 2020, this final testing was needed to keep its schedule on track for the rocket’s debut launch on the uncrewed Artemis 1 mission in mid-to-late 2021 and, ultimately, to the final crewed launch to the moon in 2024.
Although the SLS testing series started with a successful modal test – a kind of vibration testing – conducted in January 2020, the ongoing coronavirus pandemic then slowed the testing process. On-site work at Stennis was stopped by NASA leadership in March 2020, around the same time many in the U.S. began working from home, due to the coronavirus pandemic. The center began reopening slowly in mid-May, and the second SLS test was completed on the core stage (the orange “body” of the rocket) in late June.
That test ensured that the software and other electrical interfaces involved in the rocket and the testing stand work properly.
The rocket has since undergone and passed the next four steps of what is called the “green run” series:
– Test 3, in which engineers inspected all the safety systems that shut down operations during testing. During this test, they simulated potential problems.
– Test 4, the first test of each of the main propulsion system components that connect to the engines. Command and control operations were verified, and the core stage was checked for leaks in fluid or gas.
– Test 5, in which engineers ensured the thrust vector control system can move the four engines and checked all the related hydraulic systems.
– Test 6, which simulated the launch countdown, including step-by-step fueling procedures. Core stage avionics were powered on, and propellant loading and pressurization were simulated. The test team exercised and validated the countdown timeline and sequence of events.
After the January 16 hot fire test, engineers had planned to refurbish the core stage and configure it for its journey to NASA’s Kennedy Space Center in Florida, where still more tests await the core stage.
Now – with the Biden administration coming into office on January 20, 2021, and with the failure of the January 16 test – the scheduling of the Artemis program is uncertain.
Read more: How will the U.S. space program fare under President Joe Biden?
Bottom line: The failure of NASA’s SLS megarocket hot-fire test on January 16, 2021 is a clear setback for NASA’s Artemis program. The first launch in the program – an uncrewed mission called Artemis 1 – was meant to launch in late 2021. The program was meant to carry the next man and first woman back to the moon by 2024. That goal now appears unlikely.
from EarthSky https://ift.tt/397PL7Z
A planned eight-minute test firing of the four engines of NASA’s Space Launch System (SLS) – a megarocket more powerful than the Saturn V that propelled the Apollo astronauts to the moon – did not go as planned on Saturday, January 16, 2021. The test was conducted at NASA’s Stennis Space Center in Mississippi. The rocket is the one meant to launch the next man and first woman on a return to the moon by 2024 in NASA’s Artemis program. The four engines on the booster stage were supposed to fire for the eight minutes they’d need to fire during an actual launch. Instead, the engines fired for only about a minute.
NASA said in a statement:
The team successfully completed the countdown and ignited the engines, but the engines shut down a little more than one minute into the hot fire. Teams are assessing the data to determine what caused the early shutdown, and will determine a path forward.
NASA Administrator Jim Bridenstine, who attended the test, said:
Saturday’s test was an important step forward to ensure that the core stage of the SLS rocket is ready for the Artemis 1 mission [an uncrewed test mission whose launch had been planned for later this year], and to carry crew on future missions. Although the engines did not fire for the full duration, the team successfully worked through the countdown, ignited the engines, and gained valuable data to inform our path forward.
Read more from NASA about the specifics of the January 16 test of NASA’s SLS megarocket
"I want people to be encouraged because the future is very bright, and certainly we're going to learn a lot from this test." – Administrator @JimBridenstine reflects on today's hot fire of the @NASA_SLS rocket core stage. pic.twitter.com/vYfpxr56nG
— NASA (@NASA) January 17, 2021
.@NASA_SLS program manager John Honeycutt provides a summary of today's rocket core stage test at @NASAStennis: pic.twitter.com/RwpFwoiEli
— NASA (@NASA) January 17, 2021
"The test article that is behind us is also the flight hardware that will launch Orion to the Moon. This is unique. […] This article made the right decision to shut itself down." – Administrator @JimBridenstine on today's @NASA_SLS core stage test. pic.twitter.com/hv7mRx7gAn
— NASA (@NASA) January 17, 2021
The January 16 test – called a hot-fire test – was meant to be the culmination in a series of tests for the SLS megarocket. Originally scheduled to take place in early to mid-November 2020, this final testing was needed to keep its schedule on track for the rocket’s debut launch on the uncrewed Artemis 1 mission in mid-to-late 2021 and, ultimately, to the final crewed launch to the moon in 2024.
Although the SLS testing series started with a successful modal test – a kind of vibration testing – conducted in January 2020, the ongoing coronavirus pandemic then slowed the testing process. On-site work at Stennis was stopped by NASA leadership in March 2020, around the same time many in the U.S. began working from home, due to the coronavirus pandemic. The center began reopening slowly in mid-May, and the second SLS test was completed on the core stage (the orange “body” of the rocket) in late June.
That test ensured that the software and other electrical interfaces involved in the rocket and the testing stand work properly.
The rocket has since undergone and passed the next four steps of what is called the “green run” series:
– Test 3, in which engineers inspected all the safety systems that shut down operations during testing. During this test, they simulated potential problems.
– Test 4, the first test of each of the main propulsion system components that connect to the engines. Command and control operations were verified, and the core stage was checked for leaks in fluid or gas.
– Test 5, in which engineers ensured the thrust vector control system can move the four engines and checked all the related hydraulic systems.
– Test 6, which simulated the launch countdown, including step-by-step fueling procedures. Core stage avionics were powered on, and propellant loading and pressurization were simulated. The test team exercised and validated the countdown timeline and sequence of events.
After the January 16 hot fire test, engineers had planned to refurbish the core stage and configure it for its journey to NASA’s Kennedy Space Center in Florida, where still more tests await the core stage.
Now – with the Biden administration coming into office on January 20, 2021, and with the failure of the January 16 test – the scheduling of the Artemis program is uncertain.
Read more: How will the U.S. space program fare under President Joe Biden?
Bottom line: The failure of NASA’s SLS megarocket hot-fire test on January 16, 2021 is a clear setback for NASA’s Artemis program. The first launch in the program – an uncrewed mission called Artemis 1 – was meant to launch in late 2021. The program was meant to carry the next man and first woman back to the moon by 2024. That goal now appears unlikely.
from EarthSky https://ift.tt/397PL7Z
Aucun commentaire:
Enregistrer un commentaire